A successful accessory dwelling unit in Union City starts with Union City's own standards, not a checklist written for another city. The City's ADU and junior ADU (JADU) rules are in Municipal Code Chapter 18.34, adopted by Ordinance 2025-002 on March 25, 2025. That ordinance replaced the City's 2021 and 2022 ADU ordinances. The chapter says it implements Government Code Sections 66310 through 66342, and that where it conflicts with other parts of the zoning title, the ADU chapter controls.
This guide covers how to plan, design, and permit an ADU in Union City. The detailed local-rules section at the end follows Chapter 18.34 as published. Confirm current wording with the City's Planning Division before you finalize a design.
What is an ADU?
An accessory Dwelling Unit is a secondary housing unit on the same lot as a single-family or multifamily home. It is a fully functional living space with its own kitchen, bathroom, and sleeping area. Types of ADUs include:
- Detached ADU: a standalone structure separate from the primary residence. In Union City, a new detached ADU can be up to 1,200 square feet under the chapter's size table, and a smaller 800-square-foot detached unit is one of the by-right combinations on a single-family lot.
- Attached ADU: an extension connected to the primary residence, or a conversion of attached space.
- Garage Conversion: an existing garage repurposed as living space. Union City does not require you to replace parking when you demolish or convert a garage, carport, or parking space to build the ADU, and a demolition permit for a detached garage being replaced by an ADU is reviewed and issued with the ADU permit.
- Junior ADU (JADU): a unit of up to 500 square feet with an efficiency kitchen, created within the primary dwelling.
Owners use ADUs to house family members, create a long-term rental, or add flexible living space. Union City does not allow an ADU to be rented for less than 30 days.
Why build an ADU in Union City?

Chapter 18.34 gives Union City homeowners a ministerial path: every ADU and JADU needs a building permit, including conversions of existing floor area, and applications are reviewed without discretionary review or a hearing. On a lot that already has a home, the City must approve or deny a complete application within 60 days, or the application is deemed approved. Each ADU and JADU also needs its own exterior entrance, separate from the main home's, and its own address.
That framework is the practical reason to design to the Union City chapter from the start. The rules section at the end of this guide lists what the chapter allows on single-family and multifamily lots, including size, height, setbacks, fees, and JADU owner-occupancy. Where a local rule and current state law appear to differ, that section notes the state rule and recommends asking the City in writing.
Schedule a call with our ADU specialists
How should you plan an ADU in Union City?
Match the unit mix to Chapter 18.34
Confirm the lot's zoning and whether it has a single-family or multifamily dwelling. On a single-family lot, the chapter allows, in addition to one JADU, up to two ADUs: either one new attached or detached ADU, or one new detached ADU of up to 800 square feet plus one ADU converted from space inside the home or an existing accessory structure (a conversion can add up to 150 square feet only for getting in and out). Choosing that mix early keeps the plans aligned with what the City can approve ministerially.
Budget from bids and the chapter's fee rule
Construction and utility costs vary by site and unit type. This guide does not quote a construction price range. Get itemized bids from licensed professionals, and confirm current fees with the City. The chapter applies impact fees to ADUs of 750 square feet or more, charged in proportion to the main home's square footage. State law provides that no impact fee may be charged on an ADU with 750 square feet of interior livable space or less. If your unit is at or near 750 square feet, ask the City in writing how it will apply that fee rule.
Check setbacks and height before you draw
New floor area needs four-foot side and rear setbacks. The zone's front setback applies unless the ADU is 800 square feet or less, in which case no front setback applies. Conversions and same-footprint rebuilds have no setback under the chapter. Height and story limits differ for attached and detached units; they are listed in the rules section below.
What should Union City ADU plans include?

Work with a licensed architect or designer on complete plans for the building permit application, including the independent exterior entrance, the separate address, interior livable area, height, and setbacks. If the property is on the California Register of Historical Resources, exterior changes must follow the Secretary of the Interior's Standards.
- Function: size the kitchen, bath, and living areas for daily use. A JADU needs an efficiency kitchen with a cooking appliance, a food prep counter, and storage cabinets, and, if it has no bathroom of its own, an interior entry to the main living area as well as its own exterior entrance.
- Natural Light and comfort: plan windows for daylight and Insulation and energy features required by the building code at the time you apply.
- Utilities: an ADU built inside the existing home or an existing accessory structure does not need a new or separate utility connection, and no related connection fee or capacity charge applies, unless it is built with a new house or sold separately. Ask the utility agencies early what they will require for a new detached unit.
How do permits, construction, and occupancy work?
Submit a complete building permit application. If the City denies it, it must give you a full set of written comments listing what is deficient and how to fix it. If you apply for the ADU together with a new house, the City can hold the ADU decision until it decides on the house, but the ADU still gets no discretionary review. An application cannot be denied over nonconforming zoning conditions, building code violations, or unpermitted structures that do not threaten health and safety and are not affected by the ADU work.
Hire a licensed contractor and define the scope of work in the contract, including inspections, any demolition of a garage, and utility connections. Fire sprinklers are not required in the ADU if they are not required in the main home, and building an ADU does not trigger sprinklers in the existing house. The unit is not ready for occupancy until it has passed final inspection and the City has signed off.
Schedule a call with our ADU specialists
Can you rent a Union City ADU?
An ADU cannot be rented for less than 30 days, and it cannot be sold separately from the main home except as Government Code Section 66341 allows. A JADU requires a recorded deed restriction that bans selling the JADU separately and limits its size and features to what state law allows. rental income is one reason people build, but the lease and any listing have to follow the 30-day rule. The chapter's JADU owner-occupancy language is discussed in the rules section, including the current state-law limit in Government Code Section 66333.
Finish work and landscaping can support curb appeal, but they do not replace the objective standards in Chapter 18.34.
Union City's ADU rules in 2026 (Municipal Code Chapter 18.34)
The tips above are general. Here are the specific Union City rules your plans will be checked against. Union City's ADU standards are in Chapter 18.34 of the Union City Municipal Code, adopted by Ordinance No. 2025-002 on March 25, 2025, which replaced the City's 2021 and 2022 ADU ordinances. The chapter says it implements state ADU law (Gov. Code 66310 to 66342), and where it conflicts with other parts of the zoning code, the ADU chapter wins.
How approval works
- Building permit, ministerial review: every ADU and junior ADU (JADU) needs a building permit, including conversions of existing floor area. Applications are reviewed ministerially, without discretionary review or a hearing.
- 60-day clock: on a lot that already has a home, the City must approve or deny a complete application within 60 days. If it doesn't act in time, the application is deemed approved.
- Denials come with a fix list: if the City denies an application, it must give you a full set of written comments listing what's deficient and how to fix it.
- New home plus ADU: if you apply for an ADU together with a new house, the City can hold the ADU decision until it decides on the house, but the ADU still gets no discretionary review.
- Existing problems: an application can't be denied over nonconforming zoning conditions, building code violations, or unpermitted structures that don't threaten health and safety and aren't affected by the ADU work.
- Entrance and address: each ADU and JADU needs its own exterior entrance, separate from the main home's, and its own address.
How many units you can build
- Single-family lot: in addition to one JADU, up to two ADUs: either one new attached or detached ADU, or one new detached ADU of up to 800 square feet plus one ADU converted from space inside the home or an existing accessory structure (a conversion can add up to 150 square feet only for getting in and out).
- Multifamily lot, conversions: at least one ADU and up to 25% of the existing units can be created in non-livable space such as storage rooms, attics, basements, or garages.
- Multifamily lot, detached: up to eight detached ADUs on a lot with an existing multifamily building (never more than the number of existing units), or up to two on a lot with a proposed multifamily building.
Size and height
- Conversions: an ADU made from existing floor area has no size or height limit under the chapter.
- New attached ADU: up to 1,000 square feet, and up to 30 feet or the zone's height limit, never more than two stories.
- New detached ADU: up to 1,200 square feet and 16 feet tall. The limit is 18 feet within one-half mile walking distance of a major transit stop or high-quality transit corridor (plus 2 more feet, 20 feet total, to match the main home's roof pitch), or on a lot with a multifamily, multistory building.
- What counts: garages, carports, covered porches and patios, and breezeways aren't counted in the ADU's square footage.
Setbacks
- Conversions and same-footprint rebuilds: no setback applies to an ADU inside existing living space or an existing accessory structure, or one rebuilt in the same place and to the same size.
- New floor area: 4-foot side and rear setbacks. The zone's front setback applies unless the ADU is 800 square feet or less, in which case no front setback applies.
Parking
Union City doesn't apply its minimum parking requirements to ADUs at all. If you demolish or convert a garage, carport, or parking space to build the ADU, you don't have to replace that parking, and a demolition permit for a detached garage being replaced by an ADU is reviewed and issued along with the ADU permit. A JADU never needs parking, even when it's carved out of an attached garage.
Building code, sprinklers, fees, and utilities
- Occupancy: an ADU must meet the building code for detached homes, but building one isn't treated as a Group R occupancy change unless the Building Official makes a written finding of a specific health and safety impact.
- Fire sprinklers: not required in the ADU if they aren't required in the main home, and building an ADU doesn't trigger sprinklers in the existing house.
- Impact fees: the chapter applies impact fees to ADUs of 750 square feet or more, charged in proportion to the main home's square footage. Under state law (Gov. Code 66311.5, the section SB 543 renumbered from 66324, which the chapter still cites), no impact fee may be charged on an ADU with 750 square feet of interior livable space or less.
- Utilities: an ADU built inside the existing home or an existing accessory structure doesn't need a new or separate utility connection, and no related connection fee or capacity charge applies, unless it's built with a new house or sold separately.
- Historic properties: exterior changes to a structure on the California Register of Historical Resources must follow the Secretary of the Interior's Standards.
- No passageway: you don't have to provide a clear path from the street to the ADU's entrance.
Rentals and sale
- Rentals: an ADU can't be rented for less than 30 days.
- Sale: an ADU can't be sold separately from the main home except as Gov. Code 66341 allows.
JADU rules
- Size and kitchen: up to 500 square feet, with an efficiency kitchen that has a cooking appliance, a food prep counter, and storage cabinets.
- Entrances: its own exterior entrance; a JADU without its own bathroom also needs an interior entry to the main living area.
- Deed restriction: you must record a deed restriction with the City that bans selling the JADU separately and limits its size and features to what state law allows.
- Owner occupancy: the chapter requires the owner to live in the main home or the JADU. Since January 1, 2026, state law (AB 1154, Gov. Code 66333) limits owner occupancy to JADUs that share a bathroom with the main home. If your JADU has its own bathroom, ask the City in writing how it will apply this rule.
- Not a new unit: a JADU isn't treated as a separate dwelling for fire and life safety rules or for water, sewer, or power connections and fees.
Rules change, so confirm the current code with Union City's Planning Division before you finalize a design. If you'd like help working out what your lot allows, book a free consultation.
Closing Remarks
Build the Union City project around Chapter 18.34: pick a unit mix the chapter allows, design to its setbacks and height limits, and use the ministerial building permit path the ordinance provides. Confirm the current code with Planning before you submit, and ask the City in writing if a local standard and state ADU law appear to conflict.